Video – Malta’s tallest structure coming down…

Work starts on deconstruction 150-metre chimney at Delimara Power Station.

Enemalta started the dismantling of the last remaining HFO-fired power plant at the Delimara Power Station and its 150-metre chimney.

A few days ago, the company’s demolition contractors cut and removed the two large exhaust pipes connecting the plant’s heavy fuel oil (HFO) boilers to the chimney. At the same time, other workers started dismantling the first of the two boilers as well. The year-long project includes the complete demolition of the concrete and steel chimney, weighing almost 9,000 tonnes, as well as the plant’s boilers, turbines and other auxiliary installations.

Once dismantled, the plant’s materials will be carefully separated on site before they are carted away to authorised disposal sites. Over 5,400 cubic metres of concrete and other construction waste are expected to be removed from the site. Another 5,300 tonnes of metal will be exported for recycling.

The plant’s chimney structure comprises a cylindrical concrete shield rising up 50 storeys, with a base diameter of 12 metres. The concrete walls are 80 centimetres thick at the bottom and 30 centimetres on top. Inside the concrete structure there are two 2.3 metre steel exhaust pipes that emitted the smoke produced by the oil-fired boilers.

The dismantling process started with the removal of the lowermost part of these two steel pipes, which connect the chimney to the boilers. The remaining metal pipes, ladders and platforms higher up inside the chimney will be lowered to ground level using strand jacks, so that they can be safely dismantled on the ground.

At the same time, outside the chimney concrete walls, the contractors will soon start erecting an auto-lifting platform on five steel columns rising to the topmost part of the structure. Once all the metal inside the structure is removed, remote-controlled demolition robots on top of the platform will start pulling down the top 1.5 metres of the concrete walls. The platform will then be lowered 1.5 metres for the demolition robots to continue the demolition. All debris will reach the base of the chimney through the chimney itself, to minimise dust dispersion. It will then be loaded on trucks at ground level.

This process will be repeated approximately 80 times until the chimney is reduced to 35 metres. At this point, the platform will be dismantled and the remaining part of the stack will be demolished using a high reach demolition excavator from ground level.