Brown and Mason sets implosion date for two more precipitator stacks.
As part of ongoing work at Cockenzie Power Station, ScottishPower is set to demolish a further two steel precipitator structures on Tuesday, February 25, using controlled explosion.
The steel structures have a height of 34 metres and a width of 10 metres by 12.5 metres.
The full demolition programme at Cockenzie is set to run until mid-2015. The removal of the steel structures will again be managed by ScottishPower’s contractor Brown and Mason, and the controlled explosive demolition is set to take place at 2pm.
The structures are located on the seaward side of the main building and an exclusion zone will be required immediately before and after the event. This will entail the short term closure of the section of the John Muir Way that runs parallel to the sea wall.
George Camps, Project Manager at ScottishPower said: “Work at Cockenzie continues on schedule, and this will be the second controlled explosive demolition to take place.
The event will be very similar to the previous one in December, and we have been working with the local authority and the police to ensure the event is managed safely.
The 12 remaining precipitator structures will also be removed by controlled explosive demolition, which will be planned in the coming months. As previously stated, we do not expect the chimney stacks to be removed before late Autumn/Winter this year.”