Safety fears over bitter cold and high winds push back Crown Point bridge implosion.
As we exclusively revealed yesterday, today’s planned Crown Point bridge implosion has been postponed. The Vermont Agency of Transportation (VTrans) and the New York State Department of Transportation (NYSDOT) today announced that the Lake Champlain Bridge demolition has been rescheduled for Monday 28 December, at 10 a.m. due to the formation of ice on Lake Champlain and severely cold temperatures which have significantly delayed work to prepare the bridge for demolition.
Safety issues associated with the bitter cold and high winds, as well as icing around the bridge have caused the delay, according to NYSDOT’s blast subcontractor Advanced Explosives Demolition (AED). Therefore, the bridge will not be sufficiently prepared for demolition on the originally scheduled date, 23 December.
Read more here.